PLAINS TWP. — The day after an election that largely left a pro-consolidation majority intact on the Wilkes-Barre Area School Board, Superintendent Brian Costello gave a tour of the high school construction site to freshly reelected board member Shawn Walker, showing off athletic rooms already walled and roofed, beams for the gym roof going into position, and other considerable advancements in the project.

“This is good stuff,” Walker said after being impressed by the size and breadth of the project. Walker was initially critical of consolidation plans when first discussed four years ago, but his support has grown as the high school rises. He was one of three pro-consolidation incumbents on the ballot who won another term on the School Board in Tuesday’s election, which also saw two newcomers — Beth Ann Owens-Harris and Terry Schiowitz — win seats. Both have questioned the consolidation plans.

Costello eagerly discussed the variety of spaces students will have, including “flex rooms” for individual or small group work, a STEM (Science, Technology, Engineering and Math) section with state-of-the-art equipment, new space for the district’s Creative And Performing Arts Academy currently housed at GAR Memorial High School, and a heritage room in homage to the history of the three schools merging into the new one.

Critics have repeatedly questioned the projected cost savings of consolidation and accused the district of picking a former mining site that, according to tests, has some elevated levels of elements deemed hazardous in the soil. District officials have insisted the site will be safe because the project is meeting or exceeding all requirements of government regulatory agencies.

Tuesday’s election included a slate of anti-consolidation candidates, several of whom promised to stop or at least delay the project while reviewing options. The tour suggested options are narrowing. Site work is progressing quickly, with roofs appearing since the October visit, the odds seem to increase that one hoped-for milestone will be met: At least two classroom wings completed by winter so work can continue inside.

Superintendent Brian Costello, foreground left, and School Board Member Shawn Walker to his right, walk past one of several fire hydrants installed around the perimeter of the new consolidated high school in Plains Township being built for Wilkes-Barre Area School District. Walker, who initially doubted the consolidation plan, said he was impressed by the facility taking shape.
https://www.timesleader.com/wp-content/uploads/2019/11/web1_hydrant.jpg.optimal.jpgSuperintendent Brian Costello, foreground left, and School Board Member Shawn Walker to his right, walk past one of several fire hydrants installed around the perimeter of the new consolidated high school in Plains Township being built for Wilkes-Barre Area School District. Walker, who initially doubted the consolidation plan, said he was impressed by the facility taking shape. Mark Guydish | Times Leader Mark Guydish | Times Leader

Supports for the roof of the gym are being put in place at Wilkes-Barre Area’s consolidated high school site.
https://www.timesleader.com/wp-content/uploads/2019/11/web1_gym1.jpg.optimal.jpgSupports for the roof of the gym are being put in place at Wilkes-Barre Area’s consolidated high school site. Mark Guydish | Times Leader Mark Guydish | Times Leader

Barely a month after an October tour showed the walls just starting to rise, this athletic room had walls and a roof completed during a Wednesday tour. To the left, one of several large window spaces showing an expansive view of the valley is visible.
https://www.timesleader.com/wp-content/uploads/2019/11/web1_athletic-room.jpg.optimal.jpgBarely a month after an October tour showed the walls just starting to rise, this athletic room had walls and a roof completed during a Wednesday tour. To the left, one of several large window spaces showing an expansive view of the valley is visible. Mark Guydish | Times Leader Mark Guydish | Times Leader

Space for five large windows shows one of the vistas students will have in the new consolidated high school being built in Plains Township.
https://www.timesleader.com/wp-content/uploads/2019/11/web1_athletic-room-2.jpg.optimal.jpgSpace for five large windows shows one of the vistas students will have in the new consolidated high school being built in Plains Township. Mark Guydish | Times Leader Mark Guydish | Times Leader

The beginning two ramps — one on each side — being built for the auditorium stage of the new Wilkes-Barre Area consolidated high school. During a Wednesday tour, Superintendent Brian Costello noted full accessibility planned for the building, including space for a small lift into the control room of the auditorium for those unable to take the stairs.
https://www.timesleader.com/wp-content/uploads/2019/11/web1_ramps.jpg.optimal.jpgThe beginning two ramps — one on each side — being built for the auditorium stage of the new Wilkes-Barre Area consolidated high school. During a Wednesday tour, Superintendent Brian Costello noted full accessibility planned for the building, including space for a small lift into the control room of the auditorium for those unable to take the stairs. Mark Guydish | Times Leader Mark Guydish | Times Leader

Superintendent Brian Costello stands near one wing of the new consolidated Wilkes-Barre Area High School ready for the pouring of the concrete floor over a vapor barrier on the ground. A tour of the site Wednesday showed how rapidly walls have been rising once footers and floor are in place for each section of the school, being built at an estimated cost of $121 million.
https://www.timesleader.com/wp-content/uploads/2019/11/web1_floor.jpg.optimal.jpgSuperintendent Brian Costello stands near one wing of the new consolidated Wilkes-Barre Area High School ready for the pouring of the concrete floor over a vapor barrier on the ground. A tour of the site Wednesday showed how rapidly walls have been rising once footers and floor are in place for each section of the school, being built at an estimated cost of $121 million. Mark Guydish | Times Leader Mark Guydish | Times Leader
Day after election, tour shows rapid progress at W-B Area high school site

By Mark Guydish

[email protected]

Reach Mark Guydish at 570-991-6112 or on Twitter @TLMarkGuydish